The work includes the construction of a new 105-foot-wide by 145-foot-long by 15-foot-deep underground concrete wet weather storage tank located on Douglas Road in the Cawley Stadium Complex parking lot. It also involves the installation of a submersible effluent pump station for the wet weather storage tank, which includes 10 linear feet of 6-inch diameter ductile iron force main, an exterior weatherproof electrical enclosure for necessary electrical equipment, and SCADA integration. A flow diversion structure will be constructed within Douglas Road, along with 130 linear feet of 72-inch diameter reinforced concrete pipe (RCP) combined sewer overflow piping to the wet weather storage facility. Additionally, the project includes 300 linear feet of 8-inch diameter PVC gravity sanitary sewers and precast concrete manholes connecting the new underground storage tank to Douglas Road.
The work also encompasses the installation of new storm drain catch basins, water mains, and hydrants, as well as pavement repairs, surface restoration, and other appurtenant work.